OVERVIEW
Source Civil Ltd was appointed as the main contractor to carry out works to a section of pipeline which for several months was in poor condition and resulted in households being subjected to a Boil Water Notice (BWN).
SUMMARY
The works was combined into two phases and carried out in as one project which included the following:
Phase 1 – Site Investigation Works
• Carry out site investigation & Traffic Management
• Carry out a full topographical survey
• Update the proposed route on the Indicative Design Drawings
• Design connection details
Phase 2 – Mains Rehabilitation Works
• Laying of 280m of 90mm SDR 17 PE100 Water main
• Traffic Management
• Installation of associated new
• Replacement of the existing service pipes
• Construction of new chambers;
• Testing and sterilisation of the new water mains
• Reinstatement (Paving & Road)