OVERVIEW
Source were appointed as Designer, Main Contractor & PSCS to carry out the Design Build & Construction of a Water Storage Reservoir for Charles River Labs in Ballina, Mayo.
The scheme provides for the design, manufacture, supply, delivery, erection, construction, testing, commissioning of a 90 m3 water storage reservoir & ancillary pumping equipment
SUMMARY
The works comprised of the following water and construction works:
• Design, manufacture, supply, delivery, erection, construction, testing, commissioning of a 90 m3 water storage reservoir.
• Construction of access road to Water Storage Reservoir
• Tieing into the existing system without affecting the operation of the pharmaceutical plant.
• M&E Installation , Design, Testing & Commisioning of twin variable speed booster pump sets, (2XTKS 2HM5), 2 x s/s.
• Inline booster pump to take inlet water to high level with Y strainer & booster & fitted with inline digital parti flowmeter and GSM alarm.